Search found 15 matches
- Thu Oct 25, 2018 11:35 am
- Forum: Project Portfolio Risk Management
- Topic: Concurrent users
- Replies: 2
- Views: 95586
Re: Concurrent users
We have concurrent user license and it works quite well. The main issue is that if user does not logon (close RiskyProject) but keep it opened, we sometimes run out of licenses. But administrator can release the license at any time.
- Mon Mar 05, 2018 9:53 am
- Forum: Project Portfolio Risk Management
- Topic: Sorting Risk Register
- Replies: 3
- Views: 108096
Sorting Risk Register
How can I sort risk register based on risk category?
- Mon Apr 10, 2017 6:43 pm
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Importing most likely duration if it is not the base Duration in MS Project
- Replies: 1
- Views: 15841
Importing most likely duration if it is not the base Duration in MS Project
Can we import base duration from MS Project if it is different from 'duration'? What is the work around if it does not work this way?
- Thu Dec 01, 2016 4:52 pm
- Forum: Project Portfolio Risk Management
- Topic: Saving documents
- Replies: 1
- Views: 16150
Saving documents
Can we save or attach related documents to RiskyProject?
- Thu Dec 01, 2016 4:51 pm
- Forum: Project Portfolio Risk Management
- Topic: Can the Lite version be used with RiskyProject Enterprise
- Replies: 1
- Views: 15851
Can the Lite version be used with RiskyProject Enterprise
We currently have about 15 user licenses with a mixture of Professional and Lite and are considering moving to your enterprise version. Can we continue to use the Lite version with the Enterprise database.
- Fri Jul 22, 2016 2:09 pm
- Forum: Project Risk Analysis and Project Risk Management Theory
- Topic: Multiple Triggers
- Replies: 2
- Views: 29345
Multiple Triggers
Does RiskyProject support multiple triggers for the same risk?
- Fri Jul 22, 2016 2:07 pm
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Automatic Monte Carlo simulation
- Replies: 1
- Views: 18890
Automatic Monte Carlo simulation
I noticed that sometimes for smaller schedules Monte Carlo simulations are performed automatically, without pressing Calculate button? When should I press Calculate button for Monte Carlo?
- Mon Jun 27, 2016 2:35 pm
- Forum: Project Portfolio Risk Management
- Topic: Creating reports in PDF format.
- Replies: 1
- Views: 15340
Creating reports in PDF format.
Can I generate report for group of risks as PDF for RiskyProject Enterprise?
- Mon Jun 27, 2016 2:34 pm
- Forum: Project Risk Analysis and Project Risk Management Theory
- Topic: Task types
- Replies: 1
- Views: 17034
Task types
What are Fixed Units/Fixed Duration/Fixed Work
- Mon Jun 27, 2016 2:33 pm
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Recommended practices for defining low and high estimates
- Replies: 1
- Views: 18485
Recommended practices for defining low and high estimates
What are the best practices to define low and high estimates schedule or cost risk analysis?
- Wed Jun 01, 2016 11:38 am
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Importing schedule from Microsoft Project
- Replies: 1
- Views: 18768
Importing schedule from Microsoft Project
How many tasks can I import from Microsoft Project?
- Mon Sep 14, 2015 7:33 pm
- Forum: Project Portfolio Risk Management
- Topic: Changing risk register at the same time
- Replies: 1
- Views: 15360
Changing risk register at the same time
We are using RiskyProject Enterprise for portfolio risk analysis. We have 20 people using software at the same time. My question is what happen if few people update risk register at the same time. Do they overwrite each other's changes? Do you have a mechanism to prevent it?
- Mon Sep 14, 2015 7:30 pm
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Monte Carlo Simulation Convergence
- Replies: 1
- Views: 17778
Monte Carlo Simulation Convergence
I defines maximum number of simulations 2000, however simulations stop before it. I believe it is because of convergence. How does it work? How can I correctly define convergence criteria? Do you calculate convergence based on cost?
- Tue Aug 28, 2007 4:46 pm
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Corporate license
- Replies: 5
- Views: 43931
Corporate license
We are interested in buying corporate license of RiskyProject. How can we do it?
- Sun Jul 15, 2007 4:40 pm
- Forum: Project Risk Analysis and Project Risk Management Theory
- Topic: Implementation of event chain methodology
- Replies: 4
- Views: 39245
Implementation of event chain methodology
We like RiskyProject interface, but even using RiskyProject is hard to define all possible possible events, states of the activities, group of activities, resources, lags, and calendars including subscription to different events. For most real-life project, this constitutes a very significant amount...