DCMA Check #10: ResourcesThis check calculates percentage of Incomplete Tasks Percentage of Incomplete Tasks that have no Baseline Cost or Baseline Work. This check does not necessary requires resource loaded schedule. However it requires Baseline Work or Baseline Cost assigned to the task. FormulaTargetPercent of incomplete tasks with no Baseline Cost or Baseline Work 0% CommentsUsing list of task issues (the list at the top of Diagnostics dialog box) you can find tasks with "The schedule is resource loaded, but this task does not have resources assigned" or "The schedule has cost data but cost is not assigned to the task". See also |