DCMA Check #9B: Invalid Actual Dates

This check calculates percentage of Incomplete Tasks with Invalid Actual Dates: Task's Actual Start or Actual Finish after Project Status Date. Project Status dates is defined in Project Settings dialog (Schedule tab) or imported from other software, such as Microsoft Project or Primavera. Project Status date may be not defined. In this case this check will not be conducted. This check indicates how well the project schedule is updated with actuals.

Formula

DCMA Check #9B: Invalid Actual Dates

Target

Percent of incomplete tasks with Invalid Actual Dates should not exceed 0%

Comments

Using list of task issues (the list at the top of Diagnostics dialog box) you can find tasks with "Actual Start or Actual Finish after Project Status Date".

See also

DCMA Schedule Inspection