Assigning Risk Response Plans
Response plans defined in the Mitigation and Response view can be assigned to risks.
Assigning Response Plan
- Click the Risks tab. In the Risk Views group, click Risk Register.
- Double-click on risk ID to open the Risk Information dialog box.
- Click the Risk Form tab
- In the default Risk Form select a response plan from Response Plan dropdown list. These response plans are defined in Mitigation/Response view.
- If you are not using the default Risk Form, you can add the response plan dropdown list using Dropdown Edit button in Editing Mode of Risk Form.
- 6. If you don’t see your response plan in the dropdown list, it means that the response plan is not defined in the Mitigation/Response view. You still can enter Response plan name in RiskyProject, but it will not be used for risk cost calculation.