Assigning Risk Response Plans

Response plans defined in the Mitigation and Response view can be assigned to risks.

Assigning Response Plan

  1. Click the Risks tab. In the Risk Views group, click Risk Register.
  2. Double-click on risk ID to open the Risk Information dialog box.
  3. Click the Risk Form tab
  4. In the default Risk Form select a response plan from Response Plan dropdown list. These response plans are defined in Mitigation/Response view.
  5. If you are not using the default Risk Form, you can add the response plan dropdown list using Dropdown Edit button in Editing Mode of Risk Form.
  6. 6. If you don’t see your response plan in the dropdown list, it means that the response plan is not defined in the Mitigation/Response view. You still can enter Response plan name in RiskyProject, but it will not be used for risk cost calculation.

See also

Risk Form

Assigning Risk Mitigation Plans