Configuring Schedule Diagnostics

RiskyProject can perform up to 21 tests on a project schedule. By default, all of them are enabled. You can enable of disable tests, define their severity, as well as define other parameters associated with tests.

To configure schedule diagnostics:

  1. Click the Schedule tab.
  2. Select Schedule Diagnostics.
  3. Click on Configure.
  4. Enable or disable tests you want to run.
  5. Select color indicating relative severity level of each test.
  6. Select number of days for 2 tests: “Task duration is greater than …” and “Task has float greater than …”
  7. Click OK.

See also:

About Schedule Diagnostics

DCMA Schedule Inspection