Creating or modifying a base calendar

Base calendars can be created or modified in Working Time dialog (Tools menu):

  1. Click the Schedule tab. In the Schedule and Calendars group, click Working Time.
  2. Click the New button to create a new base calendar, the Delete button to remove base calendar, or the Rename button to rename base calendar
  3. Use the Working Time calendar options to modify the selected base calendar.

See also

About Calendars in RiskyProject