About Risk Assignment
Risks in RiskyProject are defined the following manner:
- Parameters: Parameters can be inputs or calculated. Input
parameters include is it Risk or Issue, is this Opened and Closed, as well as
multiple risk properties: date, owner, contact, department, area of risk, etc.
You define default risk properties in the Risk menu > Default Risk Properties.
All risks are stored in Risk Register.
- Assignment : risks can have global (to all tasks or
resources) or local (to specific task or resources) assignments. If a risk is
not assigned, the impact of the risk cannot be calculated • Mutually exclusive
alternatives: each risk assignment may have one or many mutually exclusive
alternatives. Each alternative includes chance of occurrence, outcome, outcome
result, and moment of risk.
Example Your project has a risk: Low quality of component. The risk has the
following input parameters:
- It is open
- It is a risk not an issue
- It has a number of parameters: detailed description, dates created and modified,
owner, recorder and other information.
You need to assign the risk to tasks or resources. This assignment information
will include a number of mutually exclusive alternatives for to each task the
risk is assigned.
For example, the risk is assigned to the task "Component installation" with one
alternative: Chance of occurrence 10%, Outcome: Restart Task. The risk is also
assigned to the task: "Testing" with two alternatives: Chance of occurrence 10%,
Outcome: Restart Task and Chance of occurrence 15%, Outcome Delay 2 days.
See also
About Risk Attributes
Risks in RiskyProject
|