Simulation Results View

The Simulation Results view shows the results of the probabilistic analysis of the schedule. You can use these views for the reporting and analysis of your results.

Default fields

  • Success: The chance that a task will be completed. A task can be canceled in one of 3 cases:
    • if the risk cancels task or cancel tasks + all successor has occurred • if task has reached a deadline
    • if project has reached a deadline and task finish time is beyond such deadlines.
    • success rate can be calculated in of probabilistic calculation. It equals number of iterations in which the task has been completed divided by the total number of iterations.
  • Low Duration (Mean): Low duration as a result of probabilistic calculations. It is blank for current schedule calculations. Can be minimum, P1, P5, P10. It is defined in Options (Calculation tab).
  • Mean Duration: Duration as a result of probabilistic calculations: difference between task's mean finish time and mean start time. It is blank for current schedule calculation. Please note, that "Duration Mean - result" and "Duration Mean - statistical result" can be different
  • High Duration(Mean): High duration as a result of probabilistic calculations. It is blank for current schedule calculation. Can be maximum, P90, P95, P99. It is defined in Options (Calculation tab).
  • Start Low: Low start time as a result of probabilistic calculations. It is blank for current schedule calculation. Can be minimum, P1, P5, P10. It is defined in Options (Calculation tab).Mean start time as a result of probabilistic calculations. Will have no value in the current schedule calculation.
  • Start Mean: Mean start time as a result of probabilistic calculations. Will haven o value in the current schedule calculation.
  • Start High: High start time as a result of probabilistic calculations. Will have no value in the current schedule calculation. Can be maximum, P90, P95, P99. It is defined in Options (Calculation tab)
  • Finish Low: Low mean finish time as a result of probabilistic calculations. Will have no value in the current schedule calculation. Can be minimum, P1, P5, P10. It is defined in Options (Calculation tab).
  • Finish Mean: Mean finish time as a result of probabilistic calculations. Will haven o value in the current schedule calculation.
  • Finish High: High finish time as a result of probabilistic calculations. Will have no value in the current schedule calculation. Can be maximum, P90, P95, P99. It is defined in Options (Calculation tab)
  • Low Work: The Low work units for task for the current schedule Base
  • Work: The Base work units for task for the current schedule
  • High Work : The High work units for task for the current schedule

 

Setting up reports for printing

See Setting up Reports

Printing reports

Click File Risk analysis: reporting and choose Print.

Previewing reports

Click File  Risk analysis: reporting and choose Print Preview.

See also

Setting up your projects