Professional version only
Assigning a mitigation or risk response plan to a
task
Before you can assign a mitigation or risk response plan to a task,
you must create it in the Mitigation or Response view. These
mitigation plans can be executed when a risk occurs.
- On the Workflow bar, click the Risks
tab and then the Risk Register
view.
- Double-click the risk to which you want to link the mitigation or response plan
- Click the Assign to tasks or resources tab.
- If the risk is not already assigned to a task, you must assign
the risk to the task or multiple tasks.
- Click the task to which you want to assign the plan.
- On the Selected assignment:
table, select Execute Response Plan as the Outcome for the risk. The Result field will now list all
available response plans.
- Select the response plan from the Result list.
- Repeat steps 4-6 if you want to assign the plan to additional
tasks.
You may use any risk assignment view or dialog to assign a
mitigation and response plan to a risk.
See
also
Analyzing Risk Mitigation Efforts with Multiple Baselines
Comparing pre and post-mitigation baselines
Converting a baseline to a current schedule
Creating a mitigation or risk response plans
|