Assigning a mitigation or risk response plan to a task

Before you can assign a mitigation or risk response plan to a task, you must create it in the Mitigation or Response view. These mitigation plans can be executed when a risk occurs.

  1. On the Workflow bar, click the Risks tab and then the Risk Register view.
  2. Double-click the risk to which you want to link the mitigation or response plan
  3. Click the Assign to tasks or resources tab.
  4. If the risk is not already assigned to a task, you must assign the risk to the task or multiple tasks.
  5. Click the task to which you want to assign the plan.
  6. On the Selected assignment: table, select Execute Response Plan as the Outcome for the risk. The Result field will now list all available response plans.
  7. Select the response plan from the Result list.
  8. Repeat steps 4-6 if you want to assign the plan to additional tasks.

You may use any risk assignment view or dialog to assign a mitigation and response plan to a risk.


See also

Analyzing Risk Mitigation Efforts with Multiple Baselines

Comparing pre and post-mitigation baselines

Converting a baseline to a current schedule

Creating a mitigation or risk response plans