Search Help:

Task Related Fields

Duration Low- Current Schedule

Name of parameters (shown on the tool tip)

Duration low- baseline

Type of the field

Edit Box with Spin Control

Short name (shown in the header)

Low Dur

Description

Low Task Duration is used to calculate duration on each iteration for probabilistic analysis. Particular meaning of low duration depends on statistical distribution. For example for normal and lognormal distributions, it can be P1, P5, or P10. Low duration does not affect current schedule. See "How to define distribution for Start Time, Cost, and Duration" for details.

Related Fields

Duration Base- baseline
Duration High- baseline


Legal Notice Privacy Statement Copyright © Intaver Institute Inc., 2002-. All Rights Reserved.