Name of parameters (shown on the tool tip) |
Most
likely time
of the
risk occurrence |
|
Type of the field |
Edit Box with Spin
Control |
|
Short name (shown in the
header) |
Most
Likely
|
|
Description |
Risk most likely
will
occur
at this time. Time is defined as a
percent of total task duration. For example, taskduration is 5 days. Most likely risk occurrence
of 50% means that most likely, the risk will occur at the
middle of third day. |
|
Related
Fields |
Moment of Risk Distribution chart
Finishtime of the risk occurrence Start time of the risk
occurrence
|
|