			Defining summary tasks and subtasks Summary tasks represent groups of tasks (subtasks) that can be 
			logically grouped together under a larger task. In large projects 
			with many tasks, this is a useful method of organizing your tasks.
 1. Create a task directly above the tasks that you want to group 
			under it. This will become the Summary Task.
 2. Select the tasks that you want to be the subtasks of the summary 
			task you created in step 1.
 3. Click the  Indent button located on the  Format toolbar to indent 
			the tasks. The indented tasks are automatically recognized as 
			subtasks of the summary task. If you want to move at task out from 
			under the summary task, select the task and click the Outdent 
			buttons. After you click on an Indent or Outdent button, 
			RiskyProject automatically recalculates the project.
 
 
  