Viewing the Tracking Chart


You may view a project tracking chart in the Tracking Chart view (Tracking phase). The tracking chart view is the only way you can view the tracking results for the complete project”

Once you have entered in the tracking information, the tracking chart is automatically updated to show the Baseline The original project schedule (before calculation). Baselines are calculated without taking into account risks, uncertainties, and tracking information. RiskyProject uses only one project baseline. Baseline project schedules are shown in the Baseline Gantt view. In addition, the baseline can be shown together in the Result Gantt and Tracking Gantt views. It allows you to compare the calculated project schedule, which included risks, uncertainties, and tracking information, with the baseline schedule., Low, Base, High, Actual and Forecast tracking data.
 

:

To view tracking results for specific tasks:

Select the checkbox on the right of the Task Name field. You can only view the results of one task at a time.

Notes:

See also

About Tracking

Enter Tracking Information

Calculate and Reassess Tasks Using Tracking Data

Tracking Results

About the Tracking Gantt