Tracking Results


The probabilistic calculations always encapsulate the tracking information if it has been entered for a task An activity or job which has a start date and time, an end date and time, a duration, and other properties. A Project is comprised of tasks.. RiskyProject presents results of the tracking calculations in several different ways depending upon the view Located on the left of the RiskyProject workspace, the Workflow bar allows you to quickly select and open Views. The order of the views in the workflow bar reflects the recommended project risk management workflow. The Workflow bar can be turned on and off from within the Options dialog box (view tab) or the View menu. In addition,the Workflow bar can be turned off by clicking the X in the title bar (top of workflow bar). you are using to examine it. 

View

How Tracking information is presented

Baseline The original project schedule (before calculation). Baselines are calculated without taking into account risks, uncertainties, and tracking information. RiskyProject uses only one project baseline. Baseline project schedules are shown in the Baseline Gantt view. In addition, the baseline can be shown together in the Result Gantt and Tracking Gantt views. It allows you to compare the calculated project schedule, which included risks, uncertainties, and tracking information, with the baseline schedule. Gantt

No tracking information on the baseline schedule the timing and sequence of task within a project. A schedule contains tasks with dependencies, as well as other project information.

Results Gantt

Tracking data will be presented in form of green, yellow, and red bars. These bars represent percent completed. It can be turned on and off when you right click on Gantt chart and select “Show Tracking Bars”. You can also click on  from the Standard menu.

Success Rate

Gantt chart is drawn based on baseline schedule

Critical Task

Gantt chart is drawn based on baseline schedule

Tracking Gantt

Works the same way as Results Gantt plus percent completed will be presented on the right to the bar

See also

About Tracking

Enter Tracking Information

View the Tracking Chart

Calculate and Reassess Tasks Using Tracking Data

About the Tracking Gantt