Defining Predecessors


To define different types of relationships between tasks use the four predecessor A task that must start of finish before another task starts of finishes buttons located on the standard toolbar

Different types of task An activity or job which has a start date and time, an end date and time, a duration, and other properties. A Project is comprised of tasks. dependencies are show in the following figure:

To unlink tasks:

Note:

If you want next task to be predecessor of previous task, for example task 5 to be a predecessor of task 3, you will have to use Predecessors tab in Task Information dialog box (see  About Predecessors and Lags).

Remember the following rules:

1. You cannot link summary task to one of its subtasks

2. The predecessors of a summary task must have a finish-start or start-start dependency.

3. You cannot create circular relationship

The connecting line between successors and predecessors will be red if there is a scheduling conflict:

 

See also

Overview of RiskyProject Workflow

What is RiskyProject?

RiskyProject Desktop