Calculate and Reassess Tasks Using Tracking Data


RiskyProject uses tracking information for probabilistic calculations. The purpose of the calculation is to reassess the task An activity or job which has a start date and time, an end date and time, a duration, and other properties. A Project is comprised of tasks. duration Duration: The total span of working time required completing task or whole project. Task duration can be input in months, weeks, days, hours, and minutes, as it is specified in Options dialog box (Duration tab). Internally duration is calculated in hours. Duration is calculated using current calendar. and start and finish dates based on the actual progress. As the baseline The original project schedule (before calculation). Baselines are calculated without taking into account risks, uncertainties, and tracking information. RiskyProject uses only one project baseline. Baseline project schedules are shown in the Baseline Gantt view. In addition, the baseline can be shown together in the Result Gantt and Tracking Gantt views. It allows you to compare the calculated project schedule, which included risks, uncertainties, and tracking information, with the baseline schedule. project schedule the timing and sequence of task within a project. A schedule contains tasks with dependencies, as well as other project information. remains unchanged, you can compare your original estimates with the forecasted schedule.

Probabilistic Tracking calculations are performed in the following manner:

Example

Originally, the task had a duration of 10 days and there was a 20% chance that the task would be delayed 15% or 1.5 days. However, because of tracking information, the duration was forecasted to be 20 days. In this case, the chance of the risk occurrence will in recalculated internally and reduced. However, the delay will be recalculated based on forecasted duration and now equals 3 days (20 days * 15%)

See also

About Tracking

Enter Tracking Information

View the Tracking Chart

Tracking Results

About the Tracking Gantt