Types in Events in RiskyProject
Posted: Thu Nov 24, 2005 3:31 pm
by Ken
In your articles about Event Chain Methodology you describe multiple potential events and event chain for task and resource. What events and event chains are currently implemented and RiskyProject and what events are you planning to implement on future?
Posted: Thu Nov 24, 2005 3:36 pm
by Intaver Support
RiskyProject Lite and RiskyProject professional are currently supporting the following events:
1. Restart task
2. Fixed delay (in days/weeks/...)
3. Relative delay (in percents)
4. Fixed cost increase (in dollars)
5. Relative cost increase (in percents)
6. Cancel task
7. End task
8. Cancel task and all successors
Next release will include the following events:
1. Execute mitigation plan
2. Start particular task
3. Change probability of the particular risk
4. Cancel project
Posted: Thu Nov 24, 2005 3:38 pm
by Ken
What about event related to execution of previously completed task?
Posted: Thu Nov 24, 2005 3:40 pm
by Intaver Support
"Start particular task" event will handle previously completed task. Previously completed task will be executed again and it will be reflected on the Gantt chart.