Crucial Tasks
Posted: Mon Aug 14, 2006 1:46 pm
by EsterMan
What is the diffence between critical tasks and crucial tasks?
Posted: Mon Aug 14, 2006 1:49 pm
by Intaver Support
Critical tasks are the tasks on the critical path. Crucial tasks are calculated as a result of sensitivity analysis.
Crucial Tasks are those tasks, according to the sensitivity analysis, whose duration has the most affect on a project’s duration and finish time are crucial tasks. Uncertainties related to critical tasks should be assessed and the risks associated with these tasks should be mitigated. Crucial tasks are displayed on the Gantt chart using distinct colors.
Posted: Mon Aug 14, 2006 1:56 pm
by EsterMan
Does RiskyProject calculate critical task?
Posted: Mon Aug 14, 2006 2:09 pm
by Intaver Support
RiskyProject calculates only crucial tasks. Critical tasks and crucial tasks can be different.
Posted: Mon Aug 14, 2006 2:19 pm
by EsterMan
Thank you