				Resource rate risks
				Posted: Fri Jun 09, 2017 11:03 am
				by Torelli
				Can I assign a risk to rate for resources. For example, rate can increase on 10% due to low availability of resources?
			 
			
					
				Re: Resource rate risks
				Posted: Fri Jun 09, 2017 11:17 am
				by Intaver Support
				Yes, you can use the risk outcome type: rate increase to assign a risk the a resources rate. To assign a resource rate risk, open the Resource information dialog box and click Risks. Select or enter the risk name and enter a risk chance (probability) and from the  Outcome Type drop-down list, select Rate increase. Finally add the relative impact, in this case 10%. 
 
 As you can see, it is possible to model the risk as a statistical distribution with 3 pt estimates. It is also possible to model rate uncertainties as an issue. To do this, enter 100% Chance and then a statistical distribution that model the rate uncertainty. In this case, we have shifted to most likely rate by 5 % and possible limits of a decrease of -10% or an increase of 12%.