				Define distribution for start time of the task
				Posted: Tue Oct 04, 2016 9:54 pm
				by DavidB
				Is it possible to set uncertainties for task start times?
			 
			
					
				Re: Define distribution for start time of the task
				Posted: Tue Oct 04, 2016 9:58 pm
				by Intaver Support
				Yes, however cases in which this can be used are limited such as the first activity in the project as otherwise start times are a product of the precedent network. To set uncertainty for start times on a activity, right-click on the activity ID and choose Task Information. 
- In the General tab, set Low (early) and High (late)  start times for the activity. 
 
- Click the Distributions tab.
- Select the Start Time sub tab.
- Select a distribution from the Distribution drop down list. The shape and parameters of teh charted in the Probability Density chart to the right. 
- Depending upon the distribution type, you can modify parameters (e.g. Most Likely)
- Click OK to assign the distribution.
 
			
					
				Re: Define distribution for start time of the task
				Posted: Fri Nov 04, 2016 2:10 pm
				by Fer23
				How can I see output distributions in RiskyProject Lite?
			 
			
					
				Re: Define distribution for start time of the task
				Posted: Fri Nov 04, 2016 2:14 pm
				by Intaver Support
				You cannot see output distributions (frequency charts, cumulative probability plots, etc.) in RiskyProject Lite. The exception is RiskyProject Add-in in Microsoft Project, where you can distributions for finish time, cost, and duration of project. We recommend you to upgrade to RiskyProject Professional.