Using Cost view to model proxies for non-cost items

This forum includes discussion about project risk analysis and risk management theory: Monte Carlo simulations, Event Chain Methodology, schedule and cost risk analysis. Please submit questions and case studies about your experience with our project risk analysis software.

Moderator: Intaver Support

Post Reply
G&G
Posts: 31
Joined: Tue Mar 07, 2006 3:04 pm
Location: Italy

Using Cost view to model proxies for non-cost items

Post by G&G » Thu Sep 07, 2017 3:30 pm

Can you use the Cost and Income to as proxies, for example the number of cattle/period?

Intaver Support
Posts: 989
Joined: Wed Nov 09, 2005 9:55 am

Re: Using Cost view to model proxies for non-cost items

Post by Intaver Support » Thu Sep 07, 2017 3:33 pm

Yes and we do have users who do use the cost fields as proxies for other values or units. Therefore, if you wanted to create a model that simulates the variance in the number of cattle delivered over a specific period (e.g month) you can do this simply by adding a task with a one month duration and the most likely number of cattle.

To make it more explicit, go to the Project Options > Cost and change the Currency symbol to cattle.

Image

Now, in the Cost and Income field you can create a risk model that can include low and high estimates or even risks. In this case, we are modelling the number of cattle over a 2 month period with low, most likely, and high estimates

Image

Run a simulation and you can see the results in the Cost chart. In this case, we will probably receive slightly less than we planned as the mean and P50 values are less than the most likely estimate.

Image
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com

Post Reply