Importing baselines from MS Project
Moderator: Intaver Support
Importing baselines from MS Project
Do you import all baselines for MS Project?
Re: Importing baselines from MS Project
No, RiskyProject can only import the baseline that is loaded into the project views at the time of the import. So there is no option during the transfer of Project data to RiskyProject to select a specific baseline that is not currently loaded into Microsoft Project.