Set Duration Units

Post by Jason » Wed May 25, 2016 10:19 am

Can I define project duration in minutes and how to do it?
Jason

Intaver Support
Posts: 992
Joined: Wed Nov 09, 2005 9:55 am

Re: Set Duration Units

Post by Intaver Support » Wed May 25, 2016 10:24 am

Yes, you can set duration units from minutes to months. To set your duration to units:
1. Go to Project Options and click the Duration tab.
2. From the Duration is entered in: drop down list, select the unit. In this case it would be Minutes.
Please note that if your duration units are defined in Microsoft Project and you import schedule from Microsoft Project to RiskyProject, duration units will be imported as well. Also in RiskyProject Enterprise duration units can be different for different projects.

Image
Intaver Support Team