Where is cost variance?

General discussion and questions about project risk management and risk analysis software RiskyProject. Includes discussion on how to perform efficient project risk analysis using our software.

Moderator: Intaver Support

Post Reply
Simulate167
Posts: 4
Joined: Thu Jan 03, 2008 5:55 am
Location: USA

Where is cost variance?

Post by Simulate167 » Tue Dec 01, 2015 11:25 am

We have project with actuals for schedule and cost and we can see the Actuals plotted on the chart. Why can’t I see anything for the cost variance?
Business development manager, North American Operation

Intaver Support
Posts: 992
Joined: Wed Nov 09, 2005 9:55 am

Re: Where is cost variance?

Post by Intaver Support » Tue Dec 01, 2015 11:29 am

In RiskyProject you need you Cost Analysis view. You can find in to workflow bar on right hand side under Analysis.

After you have run your Monte Carlo simulations, if you have actuals, as you have indicated you can see the Actuals plot line on the chart. You need to use the slider to show cost variance on specific time periods. By default the slider handle is located on the bottom left of the chart and you might not have noticed it. Check out the picture below.

Image
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com