Postby Ken » Wed Jul 19, 2017 8:25 pm

Can risk matrix settings be different for different users or projects?
Ken the PM

Intaver Support
Posts: 713
Joined: Wed Nov 09, 2005 9:55 am

Re: Customized risk matrix settings for different users

Postby Intaver Support » Wed Jul 19, 2017 8:27 pm

RiskyProject Enterprise version 7 supports customized risk matrix settings for different user groups or projects or portfolios.
First, you will need administrator permissions to be able to modify the Risk Matrix settings. Once you login with sufficient permissions, open a risk register for the program or group for which you want to customize the risk matrix. For example if you are the manager of a group, if you login in an modify the risk register, you can then have it assigned to your group. If you want the risk matrix applied to a certain section of the portfolio hierarchy, open the parent program and modify the risk register.

Open the Format Risk Matrix and make the desired modification (see “Formatting the Risk Matrix in the documentation”).
Click Advanced Settings and in the Advanced Risk Settings dialog box, select the Risk Matrix Settings option that you would like to apply it.

Image

By default, risk matrix settings are global, the “Risk matrix is global for all users and projects” option. Select the “Risk matrix is specific to the program/project” option if you want to apply it to the current program or project that is open. If you apply it to a program, it will be applied to all projects including sub-programs that are part of this program depending upon how many levels your hierarchy has. Selet the “Risk matrix is specific for the user or user group” if you want to apply it to the current group that your user is a part of. Groups are defined as part of the Organizational Breakdown Structure (OBS) that can be set up in the User Management module.
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com


Return to “Project Portfolio Risk Management”

Who is online

Users browsing this forum: No registered users and 1 guest