ECM and CPM

This forum includes discussion about project risk analysis and risk management theory: Monte Carlo simulations, Event Chain Methodology, schedule and cost risk analysis. Please submit questions and case studies about your experience with our project risk analysis software.

Moderator: Intaver Support

Post Reply
Karmal S.
Posts: 2
Joined: Thu May 17, 2007 10:02 am
Location: Canada

ECM and CPM

Post by Karmal S. » Mon May 28, 2007 11:30 am

Is event chain methodology an extension of Critical Path Method (CMP)? If yes, what is the difference between event chain methodology and Monte Carlo analysis of project schedules?
Karmal S.
Project Manager
New Product Development

Intaver Support
Posts: 992
Joined: Wed Nov 09, 2005 9:55 am

Post by Intaver Support » Thu Jun 07, 2007 4:39 pm

Event chain methodology is based on CPM and Monte Carlo simulation. It also includes a number of other principles which simplify modeling uncertainties in project schedules and make it much more accurate.

Among such principles:
a. Analysis of the moment of the risk
b. Managing chain of events
c. Event chain diagrams as a visualization of events
d. Recalculation of probability of events based on actual data.

Event chain methodology is an uncertainty modeling and schedule network analysis technique that is focused on identifying and managing events and event chains that affect project schedules.
PMBOK guide (Project Management Institute, 2004) includes a number of such schedule network analysis techniques:
1. CPM
2. Schedule compression
3. CCPM (Critical Chain)
4. What if scenario analysis
5. Resource leveling

Event chain methodology is another such technique. It helps to mitigate the negative impact of psychological heuristics and biases, as well as to allow for easy modeling of uncertainties in the project schedules.
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com

RNewman
Posts: 5
Joined: Mon Feb 13, 2006 2:51 pm

another question of critical event chains and CPM

Post by RNewman » Fri Mar 12, 2010 8:06 pm

Please clarify,

Are critical event chains calculated as part of critical path? That is are the critical event chains become part of the critical path or is it something entirely different?

Thanks

RN

Intaver Support
Posts: 992
Joined: Wed Nov 09, 2005 9:55 am

Critical chains and critical path

Post by Intaver Support » Tue Apr 06, 2010 9:10 am

Just to clarify, critical event chains are linked activities that due to risk events have a high potential to effect the project. Critical event chain methodology does not use CPM (critical path methodology) as it is possible that critical event chains can lie outside of the calculated critical path.
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com

RNewman
Posts: 5
Joined: Mon Feb 13, 2006 2:51 pm

Post by RNewman » Tue Apr 06, 2010 10:17 am

OK, thank you. The similar names can be confusing