Pre and Post-Mitigation Simulation Results

Posted: Mon Jul 03, 2023 5:43 pm
by Tomico
I ran Monte Carlo analysis with pre-mitigation probability and impact, and I received the results.
I can see that without mitigation the project Mechanical completion is due at a date with high probability. I also recorded the mitigation actions which reduced the probability and in some cases the impact as well. I also assigned the mitigation actions to the relevant tasks and ran again the Monte Carlo simulation but received totally the same result as I got previously.

My question that how can I see the difference between values in Finish High column? I tried to save more Baselines, but I can not make the program run the simulation with the post-mitigation probability and impact.

Re: Pre and Post-Mitigation Simulation Results

Posted: Mon Jul 03, 2023 5:49 pm
by Intaver Support
The problem appears to be that you have not created a post mitigated baseline with reduced probabilities etc due to the mitigation activities. Assigning mitigation activities in the waterfall chart are only a forecast but do not impact the simulation results. To create a post mitigated baseline, you need to create a new baseline, that have the post-mitigated probabilities and impacts as well as include the risk mitigation activities as tasks in the schedule. The procedure can be found here: http://www.intaver.com/Help4/RP_Help.ph ... ePlan.html.

Once you have created the post-mitigated baseline, select the post mitigate baseline from the Pre and Post Mitigation Baselines dialog box.