Fixed delay from 2 to 10 days

This forum includes discussion about project risk analysis and risk management theory: Monte Carlo simulations, Event Chain Methodology, schedule and cost risk analysis. Please submit questions and case studies about your experience with our project risk analysis software.

Moderator: Intaver Support

Post Reply
Hato
Posts: 20
Joined: Tue Jun 01, 2010 5:34 am
Location: US
Contact:

Fixed delay from 2 to 10 days

Post by Hato » Sun Jan 07, 2018 12:05 pm

Is any way to define risk outcome within certain margins? For example, I have a task than can be delayed in case of certain risk 2 – 10 days. I don’t know exactly on how much
Project manager

Intaver Support
Posts: 992
Joined: Wed Nov 09, 2005 9:55 am

Re: Fixed delay from 2 to 10 days

Post by Intaver Support » Sun Jan 07, 2018 12:29 pm

In order to define range of results for risk outcomes, you need to go to Options (Portfolio Options) in RiskyProject Enterprise and Enable statistical distribution of risk outcomes:

Image

This information will be saved in risk register on in database (for RiskyProject Enterprise).

Then you can define distribution type as well as low, base, and high outcomes for risk assignment in risk tab of Task Information Dialog.
Image

If you double click on risk assignment ID within Risk tab of Task Information Dialog you will be able to edit parameters for the statistical distribution of risk outcome.
Image
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com

Post Reply