Multiple Triggers

Posted: Fri Jul 22, 2016 2:09 pm
by RodHersnam
Does RiskyProject support multiple triggers for the same risk?

Re: Multiple Triggers

Posted: Fri Jul 22, 2016 2:37 pm
by Intaver Support
RiskyProject does not have multiple triggers for one risks as part of Qualitative risk analysis. Only one trigger can be applied for the risk. Triggers for qualitative risk analysis are defined using Risk Form:
- Go to Risky Register or Risk Property View
- double click on Risk ID
- Go to Property tab
- Select trigger from risk grip down list; this list will show all risks in the risk register.

Image

This trigger does not affect results of quantitative risk analysis. In quantitative risk analysis you can define risk correlation. If define that one risk is correlated with another risk, they will occur at the same time. It is not exactly trigger, because if one risk occur it does not automatically change probability of another risk.

Re: Multiple Triggers

Posted: Sun Aug 27, 2017 8:02 am
by David
I tried new version of RiskyProject 7, but it still does not have multiple triggers per one risk. I think it will be useful. I recommend to create a diagram, which shows relationship between risks.