Defining Event Chain

Posted: Sun Sep 29, 2013 4:04 pm
by Interstate
I have RiskyProject 5.0.7.1. I think it is a latest version. I have three risks:
- Bad weather: it triggers
- Equipment delivery: it triggers
- Construction delay
How can I define this chain in RiskyProject?

Re: Defining Event Chain

Posted: Sun Sep 29, 2013 4:15 pm
by Intaver Support
For quantitative analysis:
- go to any risk view (Global Risks, Local Risks for Tasks, Local Risks for Resources) or risk tabs of Task Information dialog or Resource Information dialog
- double click on risk assignment
- go to Correlation tab
- select risk, correlated with current risk
This way you can create a chain

For qualitative analysis
- go to Risk Form (double click on Risk in Risk Register)
- select trigger risk
This way the chain will not be used in Monte Calro schedule analysis.

Re: Defining Event Chain

Posted: Wed Nov 06, 2013 6:00 pm
by Tomico
If I assign the same risk to different tasks or resources, are these assignments correlated?

Re: Defining Event Chain

Posted: Wed Nov 06, 2013 6:01 pm
by Intaver Support
Yes. These assignment are correlated which each other.

Re: Defining Event Chain

Posted: Fri Apr 24, 2015 4:32 pm
by Intaver Support
In recent version 6.1 we added extra option to correlate risk assignment:

http://www.intaver.com/images/RP_RiskAssign.png

Re: Defining Event Chain

Posted: Fri Jul 10, 2015 10:06 am
by AlanZT
If have the same risk assigned to different tasks in RiskyProject, are these assignments corrected to each other or not?

Re: Defining Event Chain

Posted: Fri Jul 10, 2015 10:11 am
by Intaver Support
Risk assignments are corrected to each other by default. However you may change it by going to Schedule->Project Options->Risk tab. There is a check box there, where you can disable default correlation of risk assignments. In this case risks assigned to different tasks will occur at different moments.