Resource risks

Post by Col » Sat Mar 10, 2007 3:59 pm

I use RiskyProject to schedule my construction project. I have a number of risks related to material resources. It is mostly related to quality and delivery time.

How to do it?
Business Development Manager

Intaver Support
Posts: 992
Joined: Wed Nov 09, 2005 9:55 am

Post by Intaver Support » Sun Mar 11, 2007 10:06 am

You can assign risks to resources the same way as you assign risk to tasks. Here is the difference. The risk may occur in all tasks this risk is assigned to. If resource is used on 50% for the particular task, probability of the risk will reduce on 50%.
Intaver Support Team