Early Start, Early Finish, Late Start, Late Finish

This forum containts questions about RiskyProject project risk analysis and risk management software: features, issues, problem reports. If you have any problems or question, please submit it here.

Moderator: Intaver Support

Post Reply
MTC465
Posts: 11
Joined: Tue Jun 06, 2006 1:57 am
Location: USA

Early Start, Early Finish, Late Start, Late Finish

Post by MTC465 » Fri Dec 08, 2006 2:56 pm

I'd like to see Early Start, Early Finish, Late Start, Late Finish fields. Do you have in Lite or Professional versions?

Intaver Support
Posts: 992
Joined: Wed Nov 09, 2005 9:55 am

Post by Intaver Support » Fri Dec 08, 2006 3:33 pm

RiskyProject does not calculate Late Start and Late Finish. Start and Finish times are actually Early Start and Early Finish Time.
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com

Post Reply