Setting Chart defaults

Posted: Wed Aug 26, 2020 5:11 pm
by KerryMiller
Is there a place where you can set chart default settings? From what I can see charts settings can only be set for each project and they do not apply to new projects, that is they go back to the defaults when you first install the software.

Re: Setting Chart defaults

Posted: Wed Aug 26, 2020 5:12 pm
by Intaver Support
Currently, you can only setup chart options for specific projects. There currently isn’t a method for setting chart options that will apply to all existing or new projects.

Re: Setting Chart defaults

Posted: Tue Mar 23, 2021 1:00 pm
by Intaver Support
Chart defaults for all projects at the same time can be defined in RiskyProject Enterprise. In this case you can setup any portfolio settings, save it in database and these settings will be consistent for all projects.