Elapsed duration

Post by Fer23 » Fri Nov 04, 2016 2:02 pm

We have tasks with elapsed duration in Microsoft Project. How is it handled in RiskyProject?
Project risk management, decision and risk analysis

Intaver Support
Posts: 992
Joined: Wed Nov 09, 2005 9:55 am

Re: Elapsed duration

Post by Intaver Support » Fri Nov 04, 2016 2:28 pm

Elapsed duration is a feature of Microsoft Project. Elapsed days are used when a task’s duration needs to disregard any ‘nonworking time’ or resource constraints. For example if you need a task to be scheduled over 10 consecutive days including weekends and ignoring resource availability you could set the duration to ‘10 edays’. It is defined by symbol 'e' before duration units, although this symbol can be different for different local versions of Microsoft Project.

Recent version of RiskyProject 6.1 does not support elapsed duration directly, although new version RiskyProject 7 will support it. Currently if Microsoft Project has task duration or lag with elapsed duration RiskyProject calculates equivalent non-elapsed duration based on task start and finish times:

Image

In other words schedule with elapsed duration tasks in RiskyProject will have the same start and finish times for all tasks as in Microsoft Project, but absolute duration of these elapsed duration tasks can be different.
Intaver Support Team