Risks Assigned to the Project Schedule

This forum containts questions about RiskyProject project risk analysis and risk management software: features, issues, problem reports. If you have any problems or question, please submit it here.

Moderator: Intaver Support

Post Reply
remerson risk analysis
Posts: 8
Joined: Wed Feb 07, 2007 1:55 pm
Location: Ottawa, ON

Risks Assigned to the Project Schedule

Post by remerson risk analysis » Wed Sep 16, 2015 4:03 pm

Is there an easy way to quickly view how all project risks are assigned? As part of our project reviews we someway to show and justify our risk assignment.

Intaver Support
Posts: 992
Joined: Wed Nov 09, 2005 9:55 am

Re: Risks Assigned to the Project Schedule

Post by Intaver Support » Wed Sep 16, 2015 4:11 pm

In order to perform schedule risk analysis using Monte Carlo simulations with risk events or risk driver, you need to assign risks to tasks or resources. There are several ways to view how your risks are assigned to the project. If you would like to see the risk assignments for each task, you can go to the Task Information > Risks tab. This will list each risk that has been assigned to the task.

Image

The same is true if you would like to view which risks are assigned to particular resources. In this case, you would go to the Resources view > Resource Information> Risks. Finally, in the Report tab > Report: All Risks view you can generate a report that includes all task and resource risk assignments for each risk. This report can be printed directly from the File > Print menu, or saved in CSV format. The report can be customized to include or exclude specific risk information.
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject