Page 1 of 1

Exporting results back to Microsoft Project

Posted: Tue Mar 21, 2006 9:14 pm
by Leonardo
Can I export to Microsoft Project, my ‘result’ project schedule, the one associated with optimistic and pessimistic results?

Not at this time.

Posted: Tue Mar 21, 2006 9:30 pm
by Intaver Support
At a present time RiskyProject ex export data associated with base (mean) results of probabilistic analysis. For example, activity duration is results from 5 to 10 days. Statistical mean (average) is 7 days. This data will be exported to other applications including Microsoft Project.We are currently working on new version which is supposed to support export of an optimistic and pessimistic schedule to Microsoft Project or other applications.