Why export results back to Project

Posted: Tue Mar 21, 2006 9:13 pm
by Interstate
Why would I need to export results of analysis back to Microsoft Project?

The risk analysis can modify the original schedule

Posted: Tue Mar 21, 2006 9:29 pm
by Intaver Support
Original project schedule, created in Microsoft Project, could be different because of risk and uncertainties defined in RiskyProject. For example, during some activity, a risk has occurred. This risk will lead to increased duration of the activity and ultimately the completed project. This ‘result’ project schedule can be exported to the Microsoft Project or other applications.RiskyProject uses MPX format to export results to other application.To data as MPX format go to File -> Export. You will be presented with the selection. You can select what kind of schedule do you want to export: original (baseline) or results of analysis (with risk and uncertainties). Please note, that ‘result’ project schedule is associated with base (mean) results of probabilistic analysis