Enterprise version of RiskyProject

General discussion and questions about project risk management and risk analysis software RiskyProject. Includes discussion on how to perform efficient project risk analysis using our software.

Moderator: Intaver Support

Post Reply
PetroleumCons
Posts: 7
Joined: Tue Feb 20, 2007 10:29 pm

Enterprise version of RiskyProject

Post by PetroleumCons » Tue Jan 15, 2008 5:46 pm

We are currently looking for enterprise risk management software. It supposes to be web based risk management and risk analysis software and include the following features: risk register, qualitative risk analysis, quantitative risk analysis, and issue management. Is RiskyProject web-based or desktop-based software?

Intaver Support
Posts: 992
Joined: Wed Nov 09, 2005 9:55 am

Post by Intaver Support » Tue Jan 15, 2008 5:51 pm

Intaver Institute is activelly working on a new product called RiskyPortfolio. RiskyPorfolio is web-based software fully integrated with RiskyProject via database. Here are main features of RiskyPortfolio:

- Risk Management: risk identification, analysis, response planning
- Estimation and forecasting: perform estimation based on historical and actual data
- Tracking project with risks and uncertainties, determine what events caused the issues, and analyze effect of mitigation efforts
- Visualization and reporting

Currently RiskyProject defines project schedule, identifies project risk list,
performs quantitative risk analysis, tracks project schedule with risks and uncertainties. RiskyPortfolio will:

- Define portfolio risks
- Perform relevance analysis: find relevant historical activities and risks for project scheduling
- Provide executive dashboard: risks and project performance
- Track portfolio risks and issues; track actual duration and cost of activities
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com

PetroleumCons
Posts: 7
Joined: Tue Feb 20, 2007 10:29 pm

Post by PetroleumCons » Tue Jan 15, 2008 5:52 pm

Whare are you planning to release RiskyPortfolio?

Intaver Support
Posts: 992
Joined: Wed Nov 09, 2005 9:55 am

Post by Intaver Support » Tue Jan 15, 2008 5:53 pm

RiskyProject v. 3 will be released Q1, 2008. RiskyPortfolio will be released Q2-Q3, 2008
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com

Post Reply