Risks for resources

Posted: Mon Mar 26, 2007 4:51 pm
by Col
How can I assign risks to resources (e.g. chance that the component does not arrive on time equals 70%)?

Posted: Wed Mar 28, 2007 11:27 am
by Intaver Support
You can define local and global risks for both task and resources. To define local risks to resources:

1. Go to resource view
2. Click on resource ID, resource information dialog comes up
3. Go to Risks tab
4. Enter risks

To define global risks:

1. Go to Global risks view
2. Enter risks
3. Assign risk to all resources (use Assign column)

Re: Risks for resources

Posted: Thu Mar 06, 2014 4:39 pm
by Col
How risk impacts for resources are calculated?

Re: Risks for resources

Posted: Thu Mar 06, 2014 4:46 pm
by Intaver Support
For example, you have a risk "Software developer is sick". It cases delay on 3 days. Probability is 10%. It is assigned to resource "Software Developer". The resource is assigned to 2 tasks. For task 1 the resource is used on 100%. For task 2 the resource is used on 50%. Assigning risk to resources is essentially assigning risk tasks, where this resource is used. However risk probability will be 10% for task 1 and 5% (10% * 50%) for task 2.

Re: Risks for resources

Posted: Tue Nov 04, 2014 10:31 pm
by ProjectManager
Can I use drag'n'drop view to assign risk to resources?

Re: Risks for resources

Posted: Tue Nov 04, 2014 10:33 pm
by Intaver Support
Yes. You just need to switch radio button at the top of right pane to resources.