Rtgorwer
Posts: 21
Joined: Wed Jan 10, 2007 4:10 pm
Location: France

Risk Mitigation Tab

Post by Rtgorwer » Wed Jan 10, 2007 5:16 pm

How does risk mitigation view work in RiskyProject?

Regards,
Rtgorwer, PMP

Intaver Support
Posts: 992
Joined: Wed Nov 09, 2005 9:55 am

Post by Intaver Support » Wed Jan 10, 2007 5:22 pm

You can define mitigation plans using the Mitigation view. Mitigation plan can be execute when risk is occurred. RiskyProject will count, how many times the mitigation plan is executed. The diagram, which shows how often the mitigation plan is executed, will be displayed within a mitigation view. One mitigation plan will be executed only once per task even multiple risks occur.
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com

AlanZT
Posts: 3
Joined: Mon Nov 19, 2007 10:00 am
Location: Manchester, UK

Post by AlanZT » Tue Feb 05, 2008 12:10 pm

Here is an example. I have risk Fire and I have risk Flood. Both require clean-up and renovations. They have different probabilities, but can be assigned to the same task. However if both Fire and Flood occurred for the same task, I should be able to execute clean-up activity only once. Can I use your mitigation tab for this type of analysis?
Project Manager, PMP

Intaver Support
Posts: 992
Joined: Wed Nov 09, 2005 9:55 am

Post by Intaver Support » Tue Feb 05, 2008 12:16 pm

Yes. Risk Mitigation view is designed for such problems. Another example of this is the delay with the delivery of component. If you wait for one component, you don't necessary need to wait for another component. Here is what you can do in RiskyProject.

1. Define two risks: "Delay with delivery of the component".
2. Define outcome of this risk: "Execute Mitigation Plan"
3. Define Mitigation Plan: "Wait to component".

If both risks occurred together (both components are delayed) you need to wait only once.
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com

Ken
Posts: 65
Joined: Wed Nov 09, 2005 9:47 am
Location: California

Post by Ken » Sun Mar 09, 2008 11:10 am

I'm not sure that Mitigation is the best name for this view. I think it should be Common risks or something like this. When you develop new version just think about it.

Regards,
Ken
Ken the PM

Intaver Support
Posts: 992
Joined: Wed Nov 09, 2005 9:55 am

Post by Intaver Support » Sun Mar 09, 2008 11:17 am

Since we move towards advance managing of mitigation plans includin mitigation history, I would a good idea to rename Mitigation View. We think that this name may cause some confusion.
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com

Abraham T.
Posts: 2
Joined: Thu Jun 19, 2008 10:11 pm
Location: US

Post by Abraham T. » Tue Jun 24, 2008 5:52 pm

Hello,

Can I use your risk mitigation pan for risk response planning? Can I select different scenarios for risk response?
Abraham T.

Intaver Support
Posts: 992
Joined: Wed Nov 09, 2005 9:55 am

Post by Intaver Support » Tue Jun 24, 2008 6:17 pm

You may use Risk Mitigation view for risk mitigation planning and risk response planning. In fact most our clients use this tab particularly for risk response. Risk response planning is used to determine a course of actions after the risk has occurred.
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com

Rtgorwer
Posts: 21
Joined: Wed Jan 10, 2007 4:10 pm
Location: France

Post by Rtgorwer » Sat Oct 18, 2008 10:51 pm

Could you actually give as an example, how does it work?

Intaver Support
Posts: 992
Joined: Wed Nov 09, 2005 9:55 am

Post by Intaver Support » Sat Oct 18, 2008 11:01 pm

Let's assume that you have one task 10 days duration and two risks:
1. Increase duration on 20% chance 30%
2. Increase duration on 20% chance 50%

You frequency chart would have 3 spikes:
1. 10 days (no risks)
2. 12 days (risk 2 or risk 1)
4. 14 days (both risk 1 and risk 2)

In some cases you don't want to sum risk impact from both risks. In this case you may use risk mitigation view.

1. To go Mitigation view and enter mitigation plan "Risk Response 1" (probability 20% increase duration 20%)
2. Define risk "Execute mitigation plan" and result would be a plan name "Risk Response 1".
3. After calculation you would have only two spikes:

1. 10 days (no risks)
2. 12 days (risk 2 or risk 1, or both)
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com