sandra
Posts: 3
Joined: Sat Apr 22, 2006 10:58 am

Success Rate

Post by sandra » Tue Aug 15, 2006 7:27 pm

I downloaded RP few days ago. I like simplicity and emphasize on event rather than on statistical distributions.

Could you tell me how do you calculate success rate?

Regards,
Sandra,
Nissan Canada

Intaver Support
Posts: 992
Joined: Wed Nov 09, 2005 9:55 am

Post by Intaver Support » Tue Aug 15, 2006 7:37 pm

Success rate is reduced when task is canceled. A task can be canceled in one of three cases:


1. If the outcome Cancel task or Cancel task + all successors occurs, this cancels the tasks plus all successors which have occurred;
2. If a task reaches a deadline, and action associated with deadline is set to cancel task; and
3 If a project has reached a deadline and task finish time is beyond the deadline.
Intaver Support Team
Intaver Institute Inc.