Conditional branching

General discussion and questions about project risk management and risk analysis software RiskyProject. Includes discussion on how to perform efficient project risk analysis using our software.

Moderator: Intaver Support

Post Reply
Expert
Posts: 7
Joined: Sun Jul 09, 2006 11:11 pm

Conditional branching

Post by Expert » Sun Jul 09, 2006 11:12 pm

I'm interested RiskyProject implementation of conditional branching. How does it work in RiskyProject?

Intaver Support
Posts: 992
Joined: Wed Nov 09, 2005 9:55 am

Post by Intaver Support » Mon Jul 10, 2006 6:23 pm

Dear Expert:

Conditional branching (if then analysis) allows the project to branch from one task to another task based on certain conditions. For example, if a feature development task takes longer than 2 weeks, this may be require shorter development time for other features. Conditions related to task duration, finish time, and cost can be specified for each task that has successors. RiskyProject checks these if then conditions during simulations.

To define conditional branching:
1. Go to task information dialog (double click on task ID) for the task, which has successor.
2. Go to Branching Tab.
3. Select condition e.g If Duration >, If Cost >, etc.
4. Enter Value: e.g. Duration > 10 days
5. Enter Action: Cancel task and set duration to zero, Cancel all tasks in the branch.
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com