Page 1 of 1

How do I see which tasks most impact the project success rate

Posted: Fri Jul 13, 2018 3:59 pm
by Ken
In sensitivity view, can I see what activities affect project success rate?

Re: How do I see which tasks most impact the project success rate

Posted: Fri Jul 13, 2018 4:02 pm
by Intaver Support
Yes, if your project has a last finish time deadline, which is set in the Project Settings, you can view which activities have the most effect on your success rate of meeting the deadline.

To see which activities these are on the ribbon, click Analysis > All Views > Sensitivity Analysis
In the Sensitivity Analysis view, select Success Rate from the drop down list at the top. Now, on the bottom, select one of the task parameters (Duration, Start Time, Success Rate). This will show the tasks which have the most impact on the project success rate.
In the example below, we can the sensitivity shows us activities that can have both a negative and positive affect on the project success rate.

Image