I have three work resources assigned to work. Performed Monte Carlo simulations. I now want to see on statistical distribution of work of each resource. How to do it?

Re: Work histogram

Posted: Sun Jan 07, 2018 12:04 pm
by bbadmin
To see probability distribution of work for assigned resources you need to double click on task ID. Task information dialog will come up. Click on Resource tab and then right click on resource assignment ID. In pop up menu you select “Simulation Results”. You can view cumulative probability plot, frequency chart, or their combination. You can also view statistical summary and raw data for work in each iteration of Monte Carlo simulations.