Work histogram

General discussion and questions about project risk management and risk analysis software RiskyProject. Includes discussion on how to perform efficient project risk analysis using our software.

Moderator: Intaver Support

Hato
Posts: 19
Joined: Tue Jun 01, 2010 5:34 am
Location: US
Contact:

Work histogram

Postby Hato » Sun Jan 07, 2018 11:59 am

I have three work resources assigned to work. Performed Monte Carlo simulations. I now want to see on statistical distribution of work of each resource. How to do it?
Project manager

bbadmin
Site Admin
Posts: 15
Joined: Tue Nov 08, 2005 8:34 pm

Re: Work histogram

Postby bbadmin » Sun Jan 07, 2018 12:04 pm

To see probability distribution of work for assigned resources you need to double click on task ID. Task information dialog will come up. Click on Resource tab and then right click on resource assignment ID. In pop up menu you select “Simulation Results”. You can view cumulative probability plot, frequency chart, or their combination. You can also view statistical summary and raw data for work in each iteration of Monte Carlo simulations.

Image

Image