Resource calendars and scheduling in RiskyProject.

Post by TonyR » Sat May 20, 2017 6:17 am

How are resource calendars generated in RiskyProject?

Intaver Support
Posts: 992
Joined: Wed Nov 09, 2005 9:55 am

Re: Resource calendars and scheduling in RiskyProject.

Post by Intaver Support » Sat May 20, 2017 6:23 am

When you add a resource in RiskyProject, you select the calendar that you want to use for that resource. In the example below, the Standard project calendar has been selected.

Image

Calendars are defined in the Working Time dialog box. Once you have created the resource, you will be able to modify the resource calendar as needed. In the example below, the “resource 1” calendar is selected. You can now modify it by adding exceptions or changing working times. The resource calendar is combined with the Base calendar to calculate the schedule.

Image
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com