Post by Dwen » Fri May 05, 2017 4:02 pm

How can I restore previous baseline (baseline which I created before)?

Intaver Support
Posts: 992
Joined: Wed Nov 09, 2005 9:55 am

Re: Restore a previous baseline

Post by Intaver Support » Fri May 05, 2017 4:04 pm

In RiskyProject, if have deleted a baseline, it cannot be “restored”. If by restoring, you mean loading an existing baseline, you need to go to the Schedule tab > Baselines >Manage Baselines.
To load a baseline you must click the Current baseline checkbox associated with it. Once you select the baseline you want to restore, click OK and it will be loaded into RiskyProject (schedule, resources, costs, and risks).