Low and High Duration results

General discussion and questions about project risk management and risk analysis software RiskyProject. Includes discussion on how to perform efficient project risk analysis using our software.

Moderator: Intaver Support

Post Reply
Ken
Posts: 65
Joined: Wed Nov 09, 2005 9:47 am
Location: California

Low and High Duration results

Post by Ken » Tue May 02, 2017 9:05 pm

What is meaning of low or high duration? Is it associated with certain percentile?
Ken the PM

Intaver Support
Posts: 992
Joined: Wed Nov 09, 2005 9:55 am

Re: Low and High Duration results

Post by Intaver Support » Tue May 02, 2017 9:09 pm

When you run a simulation one of the outputs is a Low and High for duration, finish time, cost etc. In this case Low and High are percentiles that have been set in the Calculations options. By default, Low and High are set to P10 and P90. However, this can be adjusted if you like to see different percentiles.

To adjust the Low and High, go to Schedule > Project Options > Calculation. In the Low and high time, duration, and cost are calculated based on: option box, select or enter in values in the Custom Percentiles text boxes. In the example below, Low and High are set to P30 and P80 respectively.

Image
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com

Post Reply