How can I show low and high estimates of work on Gantt View?

Intaver Support
Posts: 992
Joined: Wed Nov 09, 2005 9:55 am

Re: Viewing Low and High Work

Post by Intaver Support » Mon Apr 03, 2017 10:08 am

RiskyProject comes with a Work View that displays the 3-point estimates for work based on task start time, finish time, resource allocation and calendar.

Image

The work estimates are included in columns that can be added to other views as well. For example, if you wanted to create an ad hoc report using the Tasks Sheet report you could add the work estimates by adding columns to the view > right-click on column header and choose Insert column ….
Intaver Support Team
Intaver Institute Inc.