How many tasks can I import from Microsoft Project?

Re: Importing schedule from Microsoft Project

Posted: Wed Jun 01, 2016 4:20 pm
by Intaver Support
You can import any number of tasks from Microsoft Project. The limitation is only your computer's memory. Please note that if you have integrated project schedule (with many projects and sub project) and your are working with master schedule, total integrated schedule will imported to RiskyProject. For example, if master schedule has 60 tasks, integrated schedule could have 20,000 tasks. Analysis of such schedules can make some time. Also please note that if you define project schedule in RiskyProject, maximum number of tasks is 20,000.

Image